Whether incorporated contract provisions required the main contractor to bear housing and facility rental costs for the subcontractor.
  • Contract construction — incorporated tender documents — meaning of "provide" and "bear" — avoid treating words as surplusage — intent to shift liability for housing/facility rental shown by contract price adjustments